How to Install Steel Matting in a Concrete Slab: 8 Steps for Philippine Sites

By Una Wire Products Inc. ·November 2026 ·6 min read
Quick Answer

How do you install steel matting in a concrete slab?
Compact the base, set chairs, lay the mesh on the chairs, lap sheets by at least one mesh opening (150 mm is common) and tie them with GI wire, keep 20 mm cover, then pour. Keep the mesh in the slab, not on the soil. Use boards to walk on. Always confirm gauge, slab thickness and any elevated or structural slab with your engineer.

Good mesh in the wrong place does very little. These eight steps cover how steel matting is laid for a floor slab or driveway on site, what tools you need, and the mistakes that cost the most. They match the practice in wire mesh for concrete reinforcement. If your slab is elevated or structural, follow your engineer's drawings, not this page.

Illustration of the steps for installing steel matting in a concrete slab: chairs, laying the mesh, lapping and tying, and keeping cover
Installing steel matting in a concrete slab (illustration).

8 Steps to Install Steel Matting

1. Prepare and compact the base

Remove soft soil and organic material, then compact the base and a layer of gravel. A slab only lasts as long as the ground under it.

2. Set the forms and lay a plastic sheet

Fix the forms to the slab height. Many builders lay a polyethylene sheet on the base to stop ground moisture rising into the slab.

3. Set the chairs

Place wire chairs or plastic spacers in rows, about 40 to 50 mm high for a 100 mm slab, so the mesh will sit in the slab and not on the plastic. Space them so a sheet cannot sag between them.

4. Lay the mesh on the chairs

Carry sheets flat and lay them on the chairs. A 4×8 ft sheet is a light job for two people. See the weight per sheet before you plan the carry for 6×20 ft sheets.

5. Lap the sheets

Overlap neighbouring sheets by at least one full mesh opening. 150 mm (6 inches) is a common lap on site. Lay the laps so the same sheet edge is not stacked in one line across the slab.

6. Tie the laps

Tie each lap with GI wire at the ends and a few points between, and tie the mesh to the chairs where needed so it cannot slide. Tie wire quantities are on the tie wire per roll page.

7. Cut around columns and openings

Cut the mesh around columns, pipes and openings. Cut wires flush, and keep the cut ends from pointing up into the slab surface. Keep a 20 mm gap between the mesh and the form edge.

8. Check the cover, then pour

Check that the mesh sits at the height your engineer or contractor specified and keeps at least 20 mm of concrete cover. Lay boards to walk on, pour in lifts and keep the vibrator off the mesh. Cure the slab for several days.

Tools and Materials

ItemUse
Steel matting sheetsBlack iron 2×2 inch, 3.0 – 4.5 mm for most slabs
Wire chairs or plastic spacersHold the mesh at the right height
GI tie wire and tie hookTie laps and chairs
Bolt cutter or angle grinderCut sheets to fit
Gloves and eye protectionSharp wire ends and cutting sparks
Boards or planksWalk on these during the pour
Tape measure and string lineCheck sheet layout and height

Mistakes to Avoid

  • Mesh on the ground. It does little at the bottom of a pour. Use chairs.
  • No lap, or too small a lap. Two sheets butted edge to edge are not connected.
  • Mesh pushed down by workers. Boards, not boots.
  • Exposed wire at the surface. Keep cover or the steel rusts through the slab.
  • Rust and mud on the mesh. Light surface rust is fine. Wash off mud and oil before the pour.

Frequently Asked Questions

How do you lay steel matting in a concrete slab?

Compact the base, lay a plastic sheet, set chairs, lay the mesh on the chairs, lap and tie the sheets, check the cover, then pour. Hold the mesh in the slab, not on the soil.

How much should steel matting overlap?

At least one full mesh opening, which is 2 inches for 2×2 inch mesh. On site, 150 mm (6 inches) is a common lap. Tie the lap with GI wire. Your engineer may specify more.

What do I use to hold steel matting up in the slab?

Wire chairs or plastic spacers, about 40 to 50 mm high for a 100 mm slab. Do not use stones or broken concrete.

How do I cut steel matting on site?

Use a bolt cutter for light wire, or an angle grinder with a cutting disc for 4.5 mm and above. Wear eye protection and gloves, and cut the wires flush so no sharp ends point up.

What do I tie steel matting with?

GI tie wire. Our GI wire page names #16 as a good gauge for tying rebar and mesh. A tie at every lap and a few between is usual.

See also floor slab guide, driveway guide, slab cost and GI wire.

Need the sheets cut to your slab?

We make custom sheet sizes. Send us the slab dimensions, the wire thickness and your delivery address, and we will reply with a layout, the price and what is in stock.

Get a Free Quote →
Need steel matting? Una Wire Products Inc. manufactures to standard and custom sizes. Request a free quote →

Where to next?

Ready to order? Get a quote or call (02) 8260-0181.

Viber